Public Consultation on OpenNet Interconnection Offer - Proposed Co-location Supplementary Cooling Service

13 April 2012

OpenNet submitted its proposed modifications to its ICO Schedule 12 (Co-Location Service), proposed Schedule 12B (Co-Location Supplementary Cooling Service) and Schedule 15 (Charges) for IDA's review on 5 April 2012.

OpenNet's Proposed Modifications
Schedule 12 - Co-Location Service
Schedule 12B - Co-Location Supplementary Cooling Service
Schedule 15 - Charges*
Schedule 18 - Dictionary

* OpenNet's charges for the proposed Co-Location Supplementary Cooing Service under its ICO are being reviewed by IDA.

IDA's Decision on OpenNet's Reconsideration Request

OpenNet requested IDA to reconsider the requirement in the direction dated 27 October 2011 for OpenNet to complete the Project Study in respect of a request for the Co-Location Supplementary Cooling Service under its ICO within ten business days of the date of the request and instead allow OpenNet to complete the Project Study within fifteen business days. In consideration of OpenNet's clarification that the Project Study, amongst other things, involve additional preliminary on-site survey(s) which may be required before the actual OpenNet site survey, IDA agreed to allow OpenNet an additional five business days to complete the Project Study.

IDA further agreed to OpenNet's request to remove the requirement in the direction dated 27 October 2011 on OpenNet to provide reciprocal rights to the Requesting Licensees to terminate the Co-Location Supplementary Cooling Service in the event where (i) the Central Office had become unfit for its purpose, or (ii) OpenNet's right to own, maintain or operate the Central Office was revoked or terminated or expired given that they apply only to the Co-Location Service and not to the Co-Location Supplementary Cooling Service and it is not necessary to also re-address these two scenarios in the Co-Location Supplementary Service, provided that the service in the proposed Schedule 12B (Co-Location Supplementary Cooling Service) would be terminated automatically in conjunction with the same in Schedule 12 (Co-Location Service) for the said two scenarios.

IDA issued the decision on the reconsideration request on 9 December 2011.

Request by OpenNet for Reconsideration of Certain Aspects of IDA's Direction dated 27 October 2011

On 10 November 2011, OpenNet submitted a request for IDA to reconsider certain aspects of IDA's direction dated 27 October 2011 which had required OpenNet to modify particular provisions of its ICO Schedule 12 (Co-Location Service), proposed Schedule 12B (Co-Location Supplementary Cooling Service) and Schedule 15 (Charges).

28 October 2011

Following the industry consultation on OpenNet's proposed Schedule 12B (Co-Location Supplementary Cooling Service), IDA has directed OpenNet to modify its proposal. OpenNet will have to submit to IDA a revised proposed ICO that incorporates IDA's directed modifications by 10 November 2011.

IDA's Direction - 27 October 2011
Direction
Explanatory Memo
Appendix 1 - Required Modifications to Schedule 12B
Appendix 2 - Required Modifications to Schedule 12
Appendix 3 - Required Modifications to Schedule 15

24 June 2011

OpenNet Pte Ltd (" OpenNet "), the Network Company selected to build, operate and maintain the passive infrastructure of the Next Generation Nationwide Broadband Network (" Next Gen NBN "), has proposed a set of terms and conditions to offer supplementary cooling service at its Central Offices (i.e., Schedule 12 B (Co-location Supplementary Cooling Service)) to meet the higher cooling requirements of Next Gen NBN equipment deployed by some of its Requesting Licensees.

IDA hereby invites interested parties to submit written comments regarding OpenNet's proposed Schedule 12 B.

IDA Consultation Paper
Consultation Document on Proposed Co-location Supplementary Cooling Service

Proposed ICO Schedules
Schedule 12 B (Co-location Supplementary Cooling Service)

All views and comments should be submitted in writing, and in both hard and soft copies (preferably in Microsoft Word format), and should reach IDA by 12 noon, 15 July 2011 . Respondents are required to include their personal/company particulars as well as the correspondence address in their submissions to this consultation paper. Views and comments should be addressed to:

Aileen Chia (Ms)
Deputy Director General (Telecoms & Post)
Infocomm Development Authority of Singapore
10 Pasir Panjang Road
#10-01 Mapletree Business City
Singapore 117438
Fax: +65 6211 2116

AND

Please submit soft copies, with the email header "Public Consultation on OpenNet ICO - Proposed Schedule 12B (Co-location Supplementary Cooling Service)", to this e-mail: [email protected] .

Responses Received at Closing Date - 15 July 2011
Nucleus Connect Pte Ltd
Singapore Telecommunications Limited
StarHub Ltd